Nearly done!

Works completed:
  • the paths - FINALLY!
  • 250 trees planted and under maintenance for 2 years
  • the area for ball games has been slightly increased, and the goalposts painted
  • 4,000 native plants in the garden beds under 13 week establishment period

The Playground

  • Construction is to be completed by mid September
  • Once complete, the site will be 'made good'
  • the playground is expected to re-open in mid-October

Works ahead:

  • replacement fence for the Sandridge Trugo Club
  • Grass refurbishment works
  • New lights - currently in the final stage of design - likely to be delivered later this year or early in 2010

all information thanks to Rebecca Ramage